Mindoro 40MW Geothermal Plant

Mindoro 40MW Geothermal Plant 2018-07-13T11:37:10+00:00

Project Description

CUSTOMER

  • EMERGING POWER INC

PROJECT

  • Engineering Consultancy Services, as the Owner’s Engineering Company for the design and revision of the three drilling areas designated for the Project.

TECHNICAL CARACTERISTICS

Construction Project Management works for the Surigao 11MW Bunker-Fired Diesel Power Plant Supervision of the detailed engineering stage, erection stage, and commission/start-up stage from the technical side in order to control the quality and schedule of the whole EPC project

  • Wellpads Design
  • Revision and Approval of Civil Works Designs
  • Construction and Project Management at Site, (For Civil Works)

WORKS DONE

  • Engineering Consultancy Services, as the Owner’s Engineering Company for the design and revision of the three drilling areas designated for the Project.
  • Phase I Design of Wellpads 1,2 &3
  • Phase II – Revision and Approval of Civil Works Designs
  • Revision of the proposed design and specification for the construction of the Wellpads
  • Revision of the proposed design and specification for the different Access
  • Roads to be constructed
  • Baseline Survey negotiation
  • Review the geotechnical investigations undertaken on the Wellpads
  • Review the detailed design of the Wellpads and Access Roads and sign the plans once acceptable.
  • Review and sign updated designs due to modifications made at Site.
  • Supervision of works at Site, including modifications based on new location and configuration of Wellpads, new roads design and water supply and discharge system
  • Review of supplier’s documents
  • Schedule monitoring
  • Monitoring project progress according to the agreed schedule
  • Quality and cost control of ongoing works.
  • Review and certify the completion of the works according to the contract specifications
  • Review and approval of quantity certificates prior to invoices

LOCATION

Planta Geotermal 40MW - Mindoro_4Planta Geotermal 40MW - Mindoro_3Planta Geotermal 40MW - Mindoro_2